AEW car park, Aarau
Trimming off 5 to 7 cm of existing concrete ceilings (3,000 m2) and re-profiling them. Polymer bitumen waterproofing and laying mastic asphalt surfaces. Applying new resin surface in the area of the ramp.
Trimming off 5 – 7 cm of existing concrete ceilings (3,000 m2) and re-profiling them. Polymer bitumen waterproofing and laying mastic asphalt surfaces. Applying new resin surface in the area of the ramp. Implementation according to the conventional method.
Map
Zusätzliche Dienstleistungen und Services
Unique features:
- 1,400 m carbon fibre reinforced slats
- 6,000 m² vapour-permeable protective coating ceiling soffit
- 5,000 non-impact core drill holes in ceiling soffit
Specific figures
OrganisationImplementation as individual contractor.
Construction scheduleApril - December 2008
Contract valueCHF 1.3 million
Contact for questions about the project | |
|---|---|
| Implenia Bau AG | |
| Telefon: +41 44 307 92 40 | |
| Profit Center Management civil engineering | E-Mail: info.ingenieurtiefbau@implenia.com |