Bypass AR N9, Lausanne
Resurfacing work on A9 motorway Lausanne bypass.
Resurfacing work on the A9 motorway Lausanne bypass.
Map
Divisions performance
Construction method
Depth reconstruction: 225,000.00 m2
Levelling course: 5'000.000 t ACB 11S 2,000.000 t ACB 16H
Top layer: 21,500.000 to PA 11 OFROU 4,200.000 AC MR 11 OFROU
Specialities
Use of paving machines (up to 5 machines) Night work - 21:00 to 5:00
Zusätzliche Dienstleistungen und Services
Construction management
CSD Ingénieur, Lausanne
Specific figures
Project ownerSwiss Federal Road Authority - Road Infrastructure, Estavayer-le-Lac
Amount for our servicesCHF 18 million
Construction periodJuly - September 2011