Gotthard Base Tunnel, Faido multifunction station
Heading, support and internal construction of the 2.4 km long multifunction station.
The multifunction station at Faido is 9.6 km in total, comprising crossover and longitudinal galleries, including two track cross-overs.
Map
Specific figures
Order valueCHF 1,480 million (CHF 450 million for the multifunction sation)
Construction period2001 - 2008
Length2400 m
Total excavated surface70 - 120 m2
Contact for questions about the project | |
|---|---|
| Implenia Industrial Construction | |
| Telefon: +41 43 233 39 90 | |
| E-Mail: Sandra.Guetg@implenia.com | |