Lausanne metro, lots 1100 and 1200, Lausanne
Construction of two double-track underground railway (metro) tunnels with two underground stations and lowering of the tunnel base in an existing tunnel in the city.
- Flon station 70 m
- St. Laurent station double-track tunnel 306 m
- Riponne station, length 85 m
- Construction in part using cut and cover
- Viret double-track tunnel, length 265 m
- Lowering of the tunnel base in the existing tunnel by approximately (lot 1100)
- Heading with roadheader machine for full 66 m2 cross section
- Supported with lattice arch girders and reinforced shotcrete,
- in portal areas with pipe umbrella vault.
- St. Laurent Tunnel with single-skin shotcrete construction
- Viret Tunnel with all-round sealing and
- lining in reinforced shotcrete.
- Lowering of existing tunnel: Underpinning with jetting
Map
Specific figures
Contract valueCHF 76 million
Construction period2004 - 2008
Length726 m
Total excavated surface66 m2
Contact for questions about the project | |
|---|---|