MIGROS, Neydens (F)

Construction of a complex with shopping mall, water park, fitness centre and hotel for Migros in France.

Constructed in reinforced concrete poured in situ in larges sections. Visible concrete applied from a lift: 15m high walls at 8m high pillars. Execution in self-compacting concrete using the "Stockadalles" system and shoring poles. Bench for on-site preparation of precast slabs and beams in reinforced concrete.

Map

Divisions performance

Project characteristics
INVENTORY: 6 high capacity tower cranes and truck crane, concrete mixing plant with pump and hopper.
Concrete mixed on site: 20,500.00 m3
Formwork for walls and slabs: 58,000.00 m2
Reinforcing steel: 2'000.00 t

 

Zusätzliche Dienstleistungen und Services

Architects
L35 Arquitectos Barcelona
GM2A Paris
GMAA Geneva

Engineers
Amsler & Bomblei SA / Georges Deperraz

Specific figures

Project owner

MIGROS SA, France

Amount for our services

CHF 32 million

Construction period

September 2007 to December 2008