Pont de la Poya, Fribourg

The Poya bridge in Fribourg connects Murtenstrasse with Bernstrasse as part of the H182 main road. The 851-metre long structure stretches across the Saane and the sewage plant at an average height of 70 metres above the valley floor. The 10 pillars and 2 pylons that reach a height of 110 metres form 13 bridge sections. The main distance between the pylons is 196 metres. The Palatinat approach viaduct goes directly into the Palatinat tunnel portal.

The Poya bridge in Fribourg connects Murtenstrasse with Bernstrasse as part of the H182 main road. The 851-metre long structure stretches across the Saane and the sewage plant at an average height of 70 metres above the valley floor. The 10 pillars and 2 pylons that reach a height of 110 metres form 13 bridge sections. The main distance between the pylons is 196 metres. The Palatinat approach viaduct goes directly into the Palatinat tunnel portal.

Construction method:

  • Securing the slope on the Palatinat side with bracing prior to the main work
  • Flat foundations, foundations on shafts, foundations on bored piles
  • Construction of the piles at distances of 4.2 m with large-scale formwork
  • Installation of the road plate with concrete design using a formwork carriage

The creation of the metal structure of the road plate is broken down into the following sections:

  • Palatinat approach viaduct (252.6 m) in retraction process
  • Middle bridge section designed as cable-stayed bridge by cantilever method
  • Schönberg approach viaduct (231 m) constructed successively using a heavy lifting crane

Map

Zusätzliche Dienstleistungen und Services

Unique features:

  • Securing slope with permanent injection anchors and prefabricated wall elements
  • Creation of bored piles (Ø 1.5 m, depth 15 m) and shafts (Ø 2.5 - 2.6 m, depth 10 - 13 m)
  • Cable-tensioned section: inclined cables with bundles of 31, 37 and 55

 

Specific figures

Organisation

Project implementation: joint venture

Construction schedule

March 2010 - 2013

Contract value

CHF 65 million