Gotthard Base Tunnel, Faido multifunction station

Heading, support and internal construction of the 2.4 km long multifunction station.

The multifunction station at Faido is 9.6 km in total, comprising crossover and longitudinal galleries, including two track cross-overs.

Map

Specific figures

Order value

CHF 1,480 million (CHF 450 million for the multifunction sation)

Construction period

2001 - 2008

Length

2400 m

Total excavated surface

70 - 120  m2